What painting contractor software needs to do
A painting job is won or lost on hours. On most jobs, paint is the smaller part of the bill. If your quote guesses the hours wrong, the job loses money no matter how good the finish looks. So good painting software has to do more than send a nice-looking estimate. Use this short checklist when you compare options:
- Estimate from your own production rates. A production rate is how much your crew paints in one hour, such as square feet of wall or linear feet of trim. The software should use your numbers, not someone else's.
- Price each surface its own way. Walls and ceilings by the square foot, trim by the linear foot, doors and windows by the count, prep by the hour.
- Count every hour. Drive time, loading, masking, setup and clean-up are paid hours too, so they belong in the estimate.
- Take a deposit before the start date. A paid deposit keeps your crew's week full of real work.
- Track crew hours by job. Painters clock in and out on the job, so you can check the hours you priced against the hours it took.
- Keep the job details on the painter's phone. Address, scope, colours, product notes and before/after photos.
- Keep it all in one place. The customer, quote, schedule, invoice and timesheets share one record, so nothing is typed twice.
How a painting job is priced from its real costs
Start with crew hours. Measure each surface, divide by your production rate, and add the prep, setup, drive and loading time. Multiply the total hours by the full cost of one person-hour. That is the wage plus payroll taxes, insurance and workers comp, not just the wage. Add paint and supplies, plus vehicle and fuel. That total is your job costs.
Then set the price with a margin, not a markup: price = job costs ÷ (1 − margin). Your office, ads, software and your own pay all come out of that margin. If margin and markup still feel the same, read the difference between margin and markup first. To find your true hourly cost, use the labor burden calculator.
Here is an exterior repaint of siding and trim, two coats, with a 2-person crew over 3 days. These are illustrative numbers. Your crew's rates and costs will be different.
| Item | How it is worked out | Amount |
|---|---|---|
| Prep hours | Washing, scraping and caulking | 10 hours |
| Siding hours | 1,800 sq ft × 2 coats ÷ 150 sq ft per hour | 24 hours |
| Trim hours | 400 linear ft ÷ 50 ft per hour (both coats) | 8 hours |
| Setup, masking and clean-up | 2 crew hours a day × 3 days | 6 hours |
| Drive and loading | 2 people × 1 hour × 3 days | 6 hours |
| Total crew hours | 54 hours | |
| Labor | 54 hours × $34 full cost per person-hour | $1,836 |
| Materials | Paint, primer, caulk and supplies | $650 |
| Vehicle and fuel | $25 a day × 3 days | $75 |
| Job costs | $2,561 | |
| Price at a 45% margin | $2,561 ÷ 0.55 | $4,656 |
| Left after job costs | $4,656 − $2,561 | $2,095 |
Now say the siding took 10 hours longer than you priced. That is $340 more labor at $34 an hour. What is left falls to $1,755, and your margin drops from 45% to about 38%. Nothing on the invoice tells you this happened. You only see it if crew hours are tracked by job. That is why CrewBrain records the hours on every job: so you can fix the production rate before the next quote, not after ten more jobs.
For the full method, with interior jobs, prep, coats and commercial work, read our guide on how to price and bid painting jobs. To check a quote fast, try the job price calculator. To work out a price from your own crew costs, try the free painting estimate calculator.